Sound Energy reports 2020 half year results

11/09/2020

Sound Energy, the Moroccan focused upstream oil and gas company, announces its unaudited half-year report for the six months ended 30 June 2020.

OPERATIONAL AND CORPORATE HIGHLIGHTS

  • Liquefied Natural Gas (''LNG'') Heads of Terms signed with a leading Moroccan Energy Group
  • Environmental Impact Assessment ("EIA") approvals for 120-kilometre, 20-inch pipeline and gas treatment plant/compression station received in January 2020 and March 2020 respectively
  • Successful renegotiation of the terms of the Anoual exploration permit in July 2020

FINANCIAL SUMMARY

  • Structural reduction in administrative expenses by 57% compared with H1 2019
  • Total Cash balances as at 30 June 2020 of £4.2 million
  • Equity placing to raise gross proceeds of £1.5 million at 2 pence per ordinary share announced in December 2019 and completed in January 2020
  • Equity placing post period end to successfully raise additional £3.2 million after costs at 2.125 pence per ordinary share in August 2020
  • Continued focus on disciplined cost and cash management

Despite the challenging business environment brought on by the Covid-19 global pandemic and exacerbated in the oil and gas sector by a dispute between Russia and Saudi Arabia which led to an increase in supply just as demand was falling due to the economic impact of the pandemic, the first half of 2020 was an active and productive period for the Company as it reset its strategy to transition towards becoming a cash generating Company with significant exploration potential. The period concluded with the announcement of a key milestone, that the Company had entered into a heads of terms with, and granted exclusivity to,  a Moroccan conglomerate, to provide partial financing for its Phase 1 micro LNG project and for the purchase of the LNG produced from the TE-5 Horst under the first phase of development. In addition during, the Company also received EIA approval for the Tendrara Gas Export Pipeline and Central Processing Facility (''CPF'') whilst continuing to progress the finalisation of binding terms for the proposed Gas Sales Agreement (''GSA'') with Office National de l'Electricité et de l'Eau Potable (''ONEE'') for the second phase of development of the TE-5 Horst.

Eastern Morocco Partial Disposal

The Company announced in July 2020 that it is no longer in discussions with the previously proposed purchaser in relation to the potential partial disposal of its Eastern Morocco portfolio, however, having announced its phased development strategy for the Tendrara Production Concession, the Company continues to engage with other parties who have expressed interest in participating in the Company's strategy by way of a potential farm-in. Whilst a partial disposal of its Eastern Morocco portfolio is not a strategic priority of the Company, normal business development discussions are ongoing in this regard. There is no certainty that any of these discussions will advance and the Company's current key priority is to deliver a final investment decision on its proposed Phase 1 development of the Tendrara Production Concession during 2020.

Phase 1 Micro LNG Development

In June, the Company announced that heads of terms had been entered into with a Moroccan conglomerate to permit exclusive discussions to negotiate definitive agreements for both the purchase of LNG to be produced from the TE-5 Horst as well as partial financing for the Phase 1 development by the Moroccan conglomerate. An LNG Gas Sales Agreement is currently being negotiated pursuant to which the joint venture will commit, over a 10 year period, to supply an annual contractual quantity of 100 million standard cubic metres of (liquefied) gas from the Phase 1 development, based upon the key commercial terms set out in the heads of terms.

Phase 2 Tendrara TE-5 Development

The Company continued to make progress in advancing the development of the Tendrara TE-5 discovery including the approval of the EIA mentioned above along with progression of discussions to obtain pipeline corridor rights. Despite the difficulties imposed by the Covid-19 pandemic, positive discussions with ONEE have continued in order to finalise the fully termed GSA for gas offtake. This will form a key building block to support project sanction of the proposed TE-5 Phase 2 development.

EIA of the Tendrara Gas Export Pipeline and CPF

In January 2020, the Company announced receipt of the EIA approval from the Moroccan Ministry of Energy, Mines and Environment to build and operate a 120km 20-inch gas pipeline connecting the CPF to the Gazoduc Maghreb Europe pipeline (''GME''). This was followed by the ministerial approval of the EIA for the CPF in March. Approval of the respective EIAs are important steps in the development process of the TE-5 Horst. The EIA incorporates the Micro LNG project activity.

Structural Cost Reductions

The Company continues to manage its cash resources prudently and, accordingly, having paused its operational programme in 2019, the Company continued a structural cost reduction programme aimed at materially reducing the Company's ongoing operating expenditure, including reductions in staff numbers, executive remuneration and other business costs. By the end of the reporting period, the cost reduction initiatives that have been implemented delivered a reduction in general and administrative expenses by 57% compared with the first half of 2019.

Licensing

The Company announced in July that it had successfully concluded a renegotiation of the terms of its Anoual Exploration Permit in order to realign the Company's committed exploration work programme in Eastern Morocco so that it dovetails more efficiently with the proposed phasing of our Phase 1 Development Plan at the Tendrara Production Concession in a manner that underscores both our confidence in the potential of the basin as a future significant gas producing province and our ability to deploy capital judiciously across the portfolio.

Corporate

In February, the Company announced the appointment of Graham Lyon, as Executive Chairman. The Company subsequently appointed Mohammed Seghiri as Chief Operating Officer in April. Mohammed brings extensive technical and commercial experience, as well as Moroccan knowledge and relationships which will be utilised in particular to drive forward the Company's phased development strategy in Eastern Morocco. In July, the Company announced further board strengthening with the appointment of David Blewden as an Independent non-executive director. David brings a wealth of experience from the financial side of oil and gas sector and specific experience around debt restructuring which is a key priority for the Company in the coming period. 

As at 30 June 2020, the Company had total cash balances of £4.2 million and, subsequent to the period end, the Company placed 163,529,411 new ordinary shares at a price of 2.125 pence per share to raise £3.2 million after costs in August 2020.