- Expect to place approximately $8.5 billion of projects into service in 2025, tracking to roughly 15 per cent under budget
- Announced $2.4 billion of new natural gas and nuclear power generation growth projects
TC Energy Corporation has released its first quarter results.
François Poirier, TC Energy’s President and Chief Executive Officer commented,
"As natural gas and electricity are forecasted to drive the majority of growth in final energy consumption through 2035, we are pleased to announce two new growth projects that represent strategic investments in North America’s energy future. We have approved the Northwoods project on our ANR system, designed to serve electric generation demand in the U.S. Midwest, including data centres and overall economic growth."
Demonstrating our commitment to delivering long-lived value through investment in high-quality, emission-less nuclear power generation, we have also sanctioned Unit 5 at Bruce Power for its Major Component Replacement. Backed by long-term contracts with credible counterparties and attractive build multiples1, these projects collectively highlight our disciplined strategy and our ability to capture high-value, low-risk opportunities across our portfolio."
First quarter 2025 financial results from continuing operations(2):
- Comparable earnings(3) of $1.0 billion or $0.95 per common share compared to $1.1 billion or $1.02 per common share in first quarter 2024
- Net income attributable to common shares of $1.0 billion or $0.94 per common share compared to $1.0 billion or $0.95 per common share in first quarter 2024
- Comparable EBITDA2 of $2.7 billion, similar to first quarter 2024
- Segmented earnings of $2.0 billion compared to $1.9 billion in first quarter 2024
Reaffirming 2025 outlook:
- Comparable EBITDA is expected to be $10.7 to $10.9 billion(4)
- Comparable earnings per common share (EPS) outlook remains consistent with our 2024 Annual Report, and is expected to be lower than 2024
- Capital expenditures are anticipated to be $6.1 to $6.6 billion on a gross basis, or $5.5 to $6.0 billion of net capital expenditures(5)
- Declared a quarterly dividend of $0.85 per common share for the quarter ending June 30, 2025.
Operational Highlights
- Canadian Natural Gas Pipelines deliveries averaged 27.6 Bcf/d, up eight per cent compared to first quarter 2024
- Total NGTL System deliveries set a new record of 17.8 Bcf on February 18, 2025
- Canadian Mainline receipts averaged 5.0 Bcf/d, an increase of 14 per cent compared to first quarter 2024
- U.S. Natural Gas Pipelines daily average flows were 31.0 Bcf/d, up five per cent compared to first quarter 2024
- GTN set a new all-time record of 3.2 Bcf on February 19, 2025
- Deliveries to LNG facilities averaged 3.5 Bcf/d, up five per cent compared to first quarter 2024
- Mexico Natural Gas Pipelines flows averaged 3.1 Bcf/d, six per cent higher than first quarter 2024
- Set a daily flow record of 4.1 Bcf on March 31, 2025
- Bruce Power achieved 87 per cent availability in first quarter 2025, reflecting a planned outage on Unit 5
- Cogeneration power plant fleet achieved 98.6 per cent availability in first quarter 2025, attributed to fewer forced outages and spring outages completed successfully ahead of plan.
Project Highlights
- The Southeast Gateway pipeline is ready for service. CFE has agreed to our contracted rate and accepted all requirements for in-service. Approval of our regulated rates from the Comisión Nacional de Energía (CNE) is expected by the end of May, at which time we anticipate the in-service of the Southeast Gateway pipeline. While 100 per cent of our capacity is contracted with the CFE and we have no requests for interruptible service, approval of the regulated rate by the CNE is normal course prior to commencing service. The 1.3 Bcf/d, 715-kilometre natural gas pipeline was constructed approximately 13 per cent under the original cost estimate in less than three years from the project’s final investment decision
- Approved the Northwoods project, an expansion project on our ANR system designed to provide 0.4 Bcf/d of capacity to serve natural gas-fired electric generation demand in the U.S. Midwest, including data centres and overall economic growth. The project has an anticipated in-service date of late 2029 with an estimated cost of approximately US$0.9 billion, and expects to deliver a compelling build multiple in the range of five to seven times
- Received approval of the Unit 5 Major Component Replacement (MCR) final cost and schedule estimate from the Ontario Independent Electricity System Operator (IESO) on April 2, 2025. The $1.1 billion Unit 5 MCR is expected to commence in fourth quarter 2026 with a return to service in early 2030
- ANR and GLGT each filed Section 4 Rate Cases with FERC requesting an increase to their respective maximum transportation rates expected to become effective November 1, 2025, subject to refund. We will pursue a collaborative process to find a mutually beneficial outcome with our customers through settlement.
(1) Results reflect continuing operations.
(2) Includes continuing and discontinued operations.
(3) Represents three months of Liquids Pipelines earnings in first quarter 2024 compared to Liquids Pipelines earnings of nil for the three months ended March 31, 2025. Refer to the Discontinued operations section and the 2024 Annual Report for additional information.
(4) Comparable funds generated from operations is a non-GAAP measure used throughout this news release. This measure does not have any standardized meaning under GAAP and therefore is unlikely to be comparable to similar measures presented by other companies. The most directly comparable GAAP measure is net cash provided by operations. For more information on non-GAAP measures, refer to the Non-GAAP Measures section of this news release.
(5) Capital spending reflects cash flows associated with our Capital expenditures, Capital projects in development and Contributions to equity investments.
CEO Message
Throughout the first three months of 2025, TC Energy showcased the strength of our business and our position as an industry leading natural gas and power and energy solutions company. While evolving macroeconomic conditions continue to contribute to market uncertainty, we have reaffirmed our 2025 outlook based on our highly contracted, low-risk business with 97 per cent of our comparable EBITDA underpinned by rate-regulation and/or long-term take-or-pay contracts. We delivered strong operational and financial results, achieving approximately one per cent growth in both comparable EBITDA and segmented earnings compared to first quarter 2024, despite removing a second unit from service at Bruce Power for its MCR. These results continue to demonstrate the overall resiliency of our business. We remain focused on maximizing the value of our assets through safety and operational excellence, executing our selective portfolio of growth projects and ensuring financial strength and agility as we deliver solid growth, low risk and repeatable performance for our shareholders.
The Southeast Gateway pipeline is now ready for service, representing a significant milestone in project execution. The 1.3 Bcf/d, 715-kilometre natural gas pipeline was constructed approximately 13 per cent under the original cost estimate in less than three years from the project’s final investment decision. Our partner and customer, CFE, has agreed to our contracted rate and accepted all requirements for in-service. We are jointly working with the CNE and the Secretary of Energy to obtain the approval of the regulatory rates, required for interruptible service. While 100 per cent of our capacity is contracted with the CFE and we have no requests for interruptible service, approval of the regulated rate by the CNE is normal course and required by Mexican regulation prior to commencing service. We expect to receive CNE approval by the end of May, at which time we anticipate the in-service of the Southeast Gateway pipeline. Southeast Gateway in-service will represent an important inflection point for TC Energy, contributing significant long-term contracted cash flow to our overall growth profile. The Government of Mexico has announced plans to bring approximately 29 gigawatts of new installed capacity online by 2030, including approximately 8.5 gigawatts of capacity from new natural gas plants6. The Southeast Gateway project is a critical component of this plan, strategically positioned to support operations of 10 of 14 planned natural gas power plants that support the country's transition to lower-emitting, more reliable sources of energy while driving economic growth and energy security.
As natural gas and electricity are forecasted to drive the majority of growth in final energy consumption through 2035, TC Energy's portfolio of natural gas and power assets are presented with attractive in-corridor opportunities with visibility through the end of the decade. Reflecting this opportunity, we have sanctioned the Northwoods project on our ANR system in the range of a five to seven times build multiple. Under a 20 year, take-or-pay contract, the estimated US$0.9 billion project is designed to serve natural gas-fired electric generation demand in the U.S. Midwest, including data centres and overall economic growth. The estimated in-service date of the 0.4 Bcf/d capacity project is late 2029. The Northwoods project exemplifies our strategic focus on executing high value, in-corridor, low-risk projects at attractive build multiples, underpinned by long-term take-or-pay contracts with creditworthy counterparties, allowing us to continue to deliver solid growth, low risk and repeatable performance.
Looking forward, led by a three-fold increase in LNG exports, strong growth in power generation driven by coal-to-gas conversions and data centre demand, we expect our assets will play a pivotal role in the delivery of reliable, affordable and sustainable energy. Our origination pipeline remains one of the most robust we have seen in decades, with several projects in advanced stages of development, largely related to coal-to-gas conversions and data centre demand growth. Over the past six months, we have sanctioned approximately $4 billion of new capital projects and believe we have line of sight to an increased cadence of project announcements in the second half of 2025 and into 2026. While we anticipate the majority of incremental capital would be weighted toward the end of the decade, we have added capital expenditures in 2025 and 2026 that further enhances our comparable EBITDA growth profile in 2027 and beyond, while ensuring the safety and reliability of our systems. These investments directly support service provided to our customers and their requests for capacity additions. Consistent with our disciplined approach to capital allocation, we expect projects to align with our target of five to seven times build multiples and underpinned by long-term contracts with strong counterparties.
As electricity demand in Ontario is anticipated to grow 75 per cent by 20507, Bruce Power continues play a critical role. On April 2, 2025, we received approval of the Unit 5 MCR final cost and schedule estimate from the Ontario IESO. The $1.1 billion Unit 5 MCR is expected to commence in fourth quarter 2026 with a return to service in early 2030. As we progress the refurbishment program at Bruce Power, the team remains focused on achieving the highest level of reliability, availability and safety performance at the site. On January 31, 2025, Unit 4 was removed from service to commence its MCR program, with a return to service expected in 2028. Unit 3 MCR and Unit 4 MCR continue to advance on plan for both cost and schedule. The average 2025 plant availability percentage, excluding the Unit 3 and Unit 4 MCR programs, is expected to be in the low-90 per cent range, and reflects planned maintenance on Unit 2 anticipated in the third quarter of 2025. The MCR program provides TC Energy with line of sight to meaningful growth capital at attractive returns through the end of the decade, backed by a long-term contract to 2064 with the Ontario IESO.
We continue to expect approximately $8.5 billion of projects to be placed into service in 2025, which includes the Southeast Gateway pipeline project. Our focus on project execution is a cornerstone of our strategic priorities. For the remaining projects anticipated to be placed in service in 2025, we are tracking to schedule and below initial cost estimates. High-grading projects remains a priority to optimize returns to maximize value. We will continue to sanction projects with a compelling risk/return profile to fill our $6.0 billion annual net capital expenditure limit and extend the duration of our project backlog, ensuring visibility to growth opportunities through 2030. Through this, we can continue to organically grow comparable EBITDA to support our three to five per cent dividend growth target and further reduce leverage over time.
TC Energy’s Board of Directors approved a quarterly common share dividend of $0.85 per common share for the quarter ending June 30, 2025, equivalent to $3.40 per common share on an annualized basis.