WTI (Nov) $74.38 +67c, Brent (Dec) $78.05 +43c, Diff -$3.67 -24c.
USNG (Nov) $2.85-12c, UKNG (Nov) 101.8p +2.39p, TTF (Nov) €40.485+ €0.91
Oil price
Today on this most inauspicious of anniversaries oil has rallied again to add to last weeks big gains. For the time being thoughts of supply and demand are relegated to the back of the mind and those of what might happen to Iran and its gang of associates are promoted.
It’s Africa Oil Week from Cape Town for the last time and I am having meetings with a number of companies here and will report back in due course.
Angus Energy
Angus has released a Third Quarter 2024 Production and Operations Update
- Production from the Saltfleetby Field in the Third Quarter of 2024 was 531 million standard cubic feet of natural gas and 9,977 barrels of condensate. In addition, the Brockham Field exported 1,995 barrels of oil during the Quarter.
- Gas sales of 5.85 million therms were achieved in the Quarter from the Saltfleetby Field
- Estimated revenues of £5.14m for the Quarter
Gas sales from the Saltfleetby Field equalled 5.85 million therms in aggregate for the months of July, August and September 2024, an average of 1.95 mm therms per month. Gas condensate (liquid) production averaged 109 bbl/day. Saltfleetby operational efficiency was 88% for the quarter and 2024 YTD operational efficiency has been maintained at a high level of 90%. Quarterly production and operational efficiency reflects the impact of a planned full field shutdown for five days in early July.
Oil volumes produced and sold from the Brockham Field equalled 1,995 barrels in aggregate for the months of July, August and September 2024, an average of 22 barrels/day. The field is capable of producing 25-30 barrels/day from the single well on production, with the lower quarterly volume reflecting stoppages for facilities maintenance and operational improvement work.
Hedging Update
At the start of the third quarter 2024, the monthly volumes of gas hedged under the legacy risk management programme put in place for the redevelopment of the Saltfleetby Field in 2021-22 dropped to 1.25 million therms per month from 1.5 million therms per month in the first and second quarters. These hedges will stay at this level until they expire in June 2025. Thereafter, hedges for an additional 6.44 mm therms have been struck as detailed in the table below:
Period |
Amount (therms) |
Average price (pence/therm) |
Jul 2025 |
1,085,000 |
84.41 |
Aug 2025 |
1,085,000 |
84.41 |
Sep 2025 |
1,050,000 |
84.41 |
Oct 2025 |
1,085,000 |
91.63 |
Nov 2025 |
1,050,000 |
91.63 |
Dec 2025 |
1,085,000 |
91.63 |
TOTAL |
6,440,000 |
The Company is working closely with Trafigura Trading (Europe) Sarl (“Trafigura”) on its existing hedging commitments, including the impact of previously crystallised hedges, and has the required flexibility under its financing facility with Trafigura to manage these commitments ahead of the installation of the booster compressor and the expiry of the legacy hedges.
Richard Herbert, CEO, commented:
“Angus is pleased with the production from Saltfleetby during the third quarter which extends our track record of safe, reliable production. Even with the planned maintenance shutdown in July, revenues were up on stronger gas prices. Engineering work is proceeding to plan for the installation of the third compressor (the booster compressor) in late 2024-early 2025 which is expected to raise production levels and increase ultimate recovery from the field. We are also very satisfied with the performance of the Brockham Field which has now delivered 13 tanker loads of crude oil to the market since production was restarted in late May this year.”
This was indeed another good quarter from Angus, production from Saltfleetby of 531 million scf of natural gas and 9,977 barrels of condensate. Gas sales of 5.85 million therms raised estimated revenue £5.14 in the quarter. Liquids of 109 bbl/day was very good and operational efficiency was maintained at 90% and the new compressor will add to that as such, the Brockham Field exported 1,995 barrels of oil during the Quarter, delivering an average of 22 bopd
With more good news to come Angus will be happy with another good quarter and with good news to come from production and hedging this share is seriously undervalued. All in all another good quarter and continued good progress from Angus with more to come.
Petro Matad
Petro Matad has provided the following operational update on activities in its Block XX Production Sharing Contract area in eastern Mongolia.
Highlights
- The Ministry of Industry and Mineral Resources (MIMR) and the Ministry of Construction and Urban Development (MCUD) have approved the Company’s proposal to reclassify oil production well pads such that they do not require construction permitting. MIMR has issued instructions to the Company to start production. Construction of long-term production facilities at Heron-1 has commenced and production startup during October is expected.
- Commercial details for the cooperation agreement between the Company and the operator of Block XIX facilities have been provided and are in line with expectations. As soon as the agreement is in final form it will be shared with industry regulator the Mineral Resources and Petroleum Authority of Mongolia (MRPAM) for approval.
- Preparations to test the Heron-2 well are underway with results expected in early November. Now that construction permitting is not required, the Company is progressing plans to be ready to bring the well onstream in November in the event of a good test.
- The Gobi Bear-1 exploration well has been drilled and logged. Casing has now been run to bottom and the well will be suspended pending further evaluation prior to likely well testing.
Heron-1 construction operations and production startup
Whilst mobilising to put temporary facilities on the Heron-1 well pad in order to start production and avoid further delays in the construction permitting procedure, the Company was delighted to be informed by MIMR that its proposed reclassification of oil production well pads had been approved. MIMR also issued instruction to Petro Matad to start oil production operations. The contractor, DQE Construction, is now installing the long-term production facilities with the expectation that these will be ready for production startup from Heron-1 within the month of October.
The cooperation agreement with the operator of Block XIX is progressing well and commercial terms are near final. They are in line with our expectation and understanding of the costs of the ongoing transport, processing and export operations. MRPAM has been kept informed of the negotiations and is standing by to review the agreement once it is in final form.
Heron-2 well testing
The drilling rig will be stored for the winter by contractor DQE Drilling at the Heron-2 location, making it readily available for any 2025 drilling activities the Company may decide to perform. The equipment is being stacked to avoid any impact on testing and subsequent construction operations. Well test contractor, DQE Testing, will mobilise to site once the rig is clear of the well head. Petro Matad is finalising the test programme and will perform a reservoir stimulation operation on Heron-2 prior to the well test with a view to completing the well for production provided a commercial flow rate is achieved.
Now that the lengthy construction permitting process is no longer required the chances of getting Heron-2 on stream this year have improved, and plans are being made to be ready to do so in the event of a positive well test. Suppliers of the necessary equipment have been contacted and discussions are also ongoing with the Block XIX operator with a view to borrowing spare equipment that may be available locally. The Heron-2 stimulation and testing operation is now forecast to be complete in early November, giving a short window in which to put the well on production before operational activity is suspended for the winter.
Gobi Bear-1 drilling results
The Gobi Bear-1 exploration well located in the southern part of Block XX in the Tamsag Basin has been drilled a total depth (TD) of 1,805m and wireline logging has been completed. The primary objective Lower Tsagaantsav Formation was penetrated at 1,425m and good sand development was seen. Basement was encountered at 1,741m. Drilling gas shows were seen throughout the Tsagaantsav formation and faint oil shows were also observed. Wireline logging confirmed a total of 34m of reservoir quality sandstones within a gross interval of 70m between 1,558m and 1,628m. From logs, the sands are computed to have 13% average porosity which is consistent with the productive reservoirs in the basin. Detailed log interpretation has been conducted and the resistivity profile suggests the sands may contain a hydrocarbon charge but the absence of good oil shows whilst drilling leads to some uncertainty. Without better knowledge of rock properties, water salinity and temperature at this depth, reservoir fluid determination from cuttings and logs in this well is not definitive.
In light of the ambiguous results from drilling and logging, the well has been cased to bottom and will be suspended whilst the Company gathers relevant information from well samples and regional data in the Tamsag Basin in order to refine the interpretation. The Company will then determine the forward programme, which is anticipated to involve a well test, likely being the best way to definitively determine the fluid content of the reservoirs in Gobi Bear-1.
Mike Buck, CEO of Petro Matad, said:
“The last few weeks have seen a lot of activity and some significant progress. We are extremely grateful to the recently appointed Ministers of Mining and Construction for their support in reclassifying oil production well pads to avoid the unnecessary burden of construction permitting regulations that were not designed for works of this kind. Our focus continues to be getting Heron-1 on stream as soon as possible and hopefully Heron-2 can also be brought onstream during the 2024 operational season.
The Gobi Bear-1 result is a teaser but if oil is present in these well-developed reservoirs at such easily and cheaply drillable depth that could be a very significant result for the Company. As such, suspending the well allows us to gather data to refine our understanding and determine how best to get a definitive answer.”
The Gobi Bear-1 result is indeed a bit of a mystery, or teaser as Mike Buck calls it, it may indeed be a bit of good news after a bit of time in the lab. Production at Heron-1 should happen soon and a bit of welcome good news in that extra permits are not necessary here and also that Heron-2 should creep into this year as well. If you make your own good luck then MATD have persevered hard to be rightly well deserved, good time look like they are back for Mike Buck and the team.
KeyFacts Energy Industry Directory: Malcy's Blog