Angus Energy Provides Production and Operations Update

08/01/2024

 

  • Production for the Fourth Quarter was 7.35 mm therms
  • Estimated revenues of £7.2m for the Quarter

Gas volumes produced and sold from the Saltfleetby Field equalled 7.35 mm therms in aggregate for the months of October, November and December 2023 combined, compared to 7.9 mm therms produced and sold in the third quarter. Fourth quarter production equates to an average of 2.45 mm therms per month (2.6 mm therms per month in the third quarter), as against hedged volumes of 1.5 mm therms per month for the third and fourth quarter. Operational efficiency was 87% for the fourth quarter (90% operational efficiency for the third quarter). Gas condensate (liquid) production averaged 130 bbl/day.

Map source: KeyFacts Energy

The quarter included a planned shutdown for 6 days during October for maintenance and remedial work on one of the two compressor engines on the Saltfleetby site. The compressor was returned to service on the 21st of October, allowing dual compressor operations to recommence.

The construction of the B07T permanent flowline was completed during the quarter with commissioning of the new flowline completing on the 3rd of November. B07T production losses were minimized to one day for completion of the tie-in work and for flowline commissioning activities.

A further planned intervention on one of the two compressor engines took place during November with the work successfully completed on the 22nd of November, allowing dual compressor operations to recommence.

Equipment hardware upgrades were implemented on one of the two compressor engines during December with the aim of improving engine reliability performance. Work was carried out across a small number of planned interventions prior to the festive period.

Well performance and well optimization trials were carried out during the quarter further to commissioning of the B07T permanent flowline and this work remains an ongoing focus for the sub-surface and operations team.  