13 projects selected to support green innovation and help decarbonise North Sea

24/03/2023

Crown Estate Scotland has announced the results of the world’s first leasing round designed to enable offshore wind energy to directly supply offshore oil and gas platforms.  

INTOG (Innovation and Targeted Oil & Gas) leasing aims to attract investment in innovative offshore wind projects in Scottish waters, as well as help decarbonise North Sea operations.   

The INTOG process allowed developers to apply for seabed rights to develop offshore wind projects that either reduce emissions from the North Sea oil and gas sector - by supplying renewable electricity directly to oil and gas infrastructure (TOG) - or consist of small-scale (IN) innovative projects of 100MW or less.  This distinctive offshore wind leasing is different to any other previously carried out in the UK or in the world. 

INTOG, which has been designed in response to demand from government and industry to help achieve the targets of the North Sea Transition Sector Deal through decarbonising North Sea oil and gas operations, will also further stimulate innovation in Scotland’s offshore wind sector, create additional supply chain opportunity, assist companies to enter the renewable energy market, and support net-zero ambitions. 

The successful applicants have now been offered initial agreements – called Exclusivity Agreements – that, if they accept the offers and proceed to sign them, enable them to start offshore wind development work while the Marine Scotland’s planning process for the INTOG Sectoral Marine Plan (INTOG SMP) is completed.  

If a successful proposed project is in the final INTOG SMP, an option agreement will be offered. Projects will then go through planning, consenting, and financing stages. Responsibility for these next steps does not sit with Crown Estate Scotland, and projects will only progress to a full seabed lease once all these various planning stages have been completed.    

Highlights include:  

13 projects out of a total of 19 applications - five for IN and eight for TOG - have been offered Exclusivity Agreements. 

Once the Sectoral Marine Plan has been finalised and option agreements signed (expected 2024), around £262m in applicant fees will be secured. Once projects are operating, further revenues will be secured. All net revenues from Crown Estate Scotland go to Scottish Government for public spending.  

The area of seabed covered by the IN projects is just over 139km2 and by the TOG projects 1534km² (a maximum of 1900km² was made available for TOG projects and 167km² for IN through the Scottish Government’s Initial Plan Framework.)  

Crown Estate Scotland will offer a seabed lease of 50 years for TOG projects and 25 years for IN projects. 

Exclusivity Agreements will cover projects with a proposed capacity of up to 499MW for IN and 5GW for TOG.  

The details of the 13 applicants who have been offered Exclusivity Agreements can be found below.

 Lead applicant  Option Fees  IN or  TOG Total capacity  (MW)
 Bluefloat Energy/Renantis Partnership  £5,401,360  IN  99.45
 Bluefloat Energy/Renantis Partnership  £7,107,900  IN  99.45
 Simply Blue Energy  £9,972,000  IN  100
 BP Alternative Energy Investments  £1,670,917  IN  50
 ESB Asset Development UK   £3,137,000  IN  100
 Flotation Energy   £54,893,102  TOG  560
 Flotation Energy  £40,987,979  TOG  1350
 Cerulean Winds  £67,200,066  TOG  1008
 Cerulean Winds  £35,200,098  TOG  1008
 Cerulean Winds  £35,200,098  TOG  1008
 TotalEnergies  £200,000  TOG  3
 Harbour Energy   £405,000  TOG  15
 Harbour Energy   £405,000  TOG  15
 Total (rounded)  £261,780,521    


About INTOG

Innovation and Targeted Oil & Gas (INTOG) is a leasing round for offshore wind projects that will directly reduce emissions from oil & gas production and boost further innovation. 

Developers can apply for seabed rights to build two types of offshore wind project: 

  • IN - Small scale, innovative projects, of less than 100MW 
  • TOG - Projects connected directly to oil and gas infrastructure, to provide electricity and reduce the carbon emissions associated with production  

INTOG is designed, in response to demand from government and industry, to help achieve the targets of the North Sea Transition Sector Deal. 