Energy Country Review: Complimentary 7-day trial

  • News-alert sign up
  • Contact us

Kosmos Energy Provides Operational Update

06/07/2021

Kosmos Energy today provided an operational update on its production, development and exploration activities. This is in advance of the Company’s second quarter results, which are scheduled for release on August 9, 2021.

Andrew G. Inglis, Chairman and Chief Executive Officer of Kosmos said:
“Kosmos had a solid second quarter, generating positive cash flow which reduced net debt by around $100 million, driven by higher sales volumes, strong operational performance in Ghana and improving realized oil prices. We continue to see momentum build across our producing hubs with new wells drilled in Ghana and the U.S. Gulf of Mexico during the quarter and the arrival of the rig for development drilling in Equatorial Guinea.

“In Mauritania and Senegal, the Greater Tortue Ahmeyim project continued to make steady progress during the quarter with key milestones achieved across all major workstreams. However, we are seeing cost inflation and supplier delays in the current environment together with some scope growth and, as a result, we are updating our estimates, with first gas now expected in the third quarter of 2023. Tortue is the right project at the right time with Phases 1 & 2 expected to deliver attractive returns in a strengthening LNG market.

“Kosmos has an active second half of the year with planned infill wells in all three hubs supporting our near-term production growth. We also expect to restart exploration and appraisal drilling in the U.S. Gulf of Mexico this quarter with the Winterfell appraisal and Zora ILX wells.

With rising oil prices and a robust financial position, we are well placed to create shareholder value through the rest of 2021.” 1

Operational Update

Sales volumes in the second quarter averaged around 66,000 barrels of oil equivalent per day (boepd) with 4.5 cargos lifted, in line with guidance.

Total net production in the second quarter averaged approximately 52,000 boepd, slightly below prior guidance primarily due to lower production in Equatorial Guinea.

Full year company production guidance of 53,000-57,000 boepd is unchanged with a year-end exit rate of approximately 60,000 boepd expected as new wells come online.

Ghana

In Ghana, performance in the quarter was strong with gross production of approximately 106,000 barrels of oil per day (bopd) in the second quarter (22,000 bopd net) including 71,000 bopd at Jubilee and 35,000 bopd at TEN.

The first two wells in our four-well campaign have been drilled and the rig has now begun completion operations. The first Jubilee producer well (J-56P) is expected online shortly and the Jubilee injector well (J-55W) is expected online later in the third quarter. These wells are expected to add gross production of around 15,000-20,000 bopd. The rig is then scheduled to drill and complete a TEN gas injector well and a second Jubilee producer well later in the year with the Jubilee producer well expected online around the end of the year.

The reliability of the Ghana production facilities continues to improve, with uptime of the Jubilee and TEN floating production, storage and offtake vessels (FPSOs) averaging about 98% year-to-date.

Consistently high levels of water injection (>200,000 barrels/day) and gas offtake from the Government of Ghana (>110 mmscf/day) are helping to optimize reservoir performance at Jubilee, which is expected to support long-term production levels.

Equatorial Guinea 

In Equatorial Guinea, gross production averaged around 29,000 bopd in the second quarter with significant downtime related to facilities upgrades which are now substantially complete. Net production was 9,400 bopd, also impacted by lower entitlement as a result of higher oil prices. The drilling rig arrived in late June and has started drilling the first of three infill wells planned for 2021. Once online, these wells are expected to add gross production of around 4,000 bopd.

U.S. Gulf of Mexico

In the U.S. Gulf of Mexico, net production averaged around 20,300 boepd in the second quarter, in line with the first quarter. In April, the Kodiak-3 infill well was brought online with one of two zones intermittently producing. We are currently working with our partners to evaluate the best intervention options to enhance production from the first zone and enable production from the second zone. In June, the operator announced the successful drilling of the Tornado-5 infill well, with results consistent with expectations. The well is expected to add around 8,000-10,000 boepd gross with planned start-up in the third quarter.

Earlier in the year, Kosmos and its partners made the Winterfell discovery in the U.S. Gulf of Mexico with the first appraisal well planned for the third quarter.

Kosmos also plans to drill the Zora infrastructure-led exploration (ILX) well early in the third quarter and a rig has been contracted for this activity.

Mauritania & Senegal

The Greater Tortue Ahmeyim (“GTA”) liquified natural gas (LNG) project has made steady progress year-to-date with the following milestones achieved in the second quarter:

  • Floating LNG vessel: The four remaining sponsons have been integrated in the final dry dock
  • FPSO: The living quarters have been installed
  • Breakwater: Five caissons have now been transported offshore with the first caisson installed
  • Subsea: All subsea trees have been constructed

Project partners have received a revised forecast from the EPCIC contractor, TechnipFMC, that the delivery of the FPSO is likely to be slightly delayed due to labor shortages at the COSCO yard in China following a ramp up in activity at the shipyard as the pandemic recedes. This delay, currently anticipated to be around three months, is expected to push the timing of first gas to the third quarter of 2023.

BP, as operator of the GTA project, has informed partners that due to the impacts of COVID-19 (including the FPSO delay), cost inflation and scope growth, Phase 1 project costs are expected to increase. On the basis of the revised schedule, Kosmos currently expects the gross cost for the project to be approximately 15% higher, resulting in an estimated increase of Phase 1 costs to first gas net to Kosmos of around $100 million, coming primarily in 2023.

The FPSO sale and lease back transaction is now expected to close this quarter upon the finalization of the documentation between the governments and partners. Following the closing of the FPSO sale and lease back transaction, the company will work to complete the re-financing of the National Oil Company loans.

In addition, partners continue to make progress on Phase 2 of the GTA LNG project and we are targeting a final investment decision in late 2022 as previously communicated.

Financial Update

Following the completion of the $450 million senior notes issuance in March and the reserve-based lending amendment and extension in May, Kosmos has a robust financial position and increased liquidity. At the end of the second quarter, Kosmos had total liquidity of over $775 million.

The Company is currently around 60% hedged for the remainder of 2021 with growing exposure to higher oil prices as hedges roll off. We have taken advantage of rising oil prices to hedge 4.5 million barrels of 2022 production.

Tags:
< Previous Next >